6030 House panel progress
3 sides of the house are done now.
One more wall and then the roof will begin. They saved the easiest wall to access for last so it should go faster than the other 3.
Photos of the panel installation are up on the 6030 House Flickr set. I apologize that this page is getting so long to load - bad web manners. Dial-up please beware.
Continue reading "6030 House panel progress"
Photos of today's activity are up on the
Photos of today's activity are up on the
Strange as it may sound, windows go in before the walls in this house. Photos of today's activity are up on the
The plywood floor deck went down over the past two days along with some other misc work. I have to say that these floor joists and the plywood deck were the slowest part of the build so far. The alternative of steel bar joists and steel deck would have gone in faster I am quite confident. A small observation about carpentry vs steel. Photos of today's activity are up on the
The last of the framing work went in today - a few loose ends to finish tomorrow, but panels should begin. Photos of today's activity are up on the
Apparently an EcoSteel install crew knows no rest, as these guys were out there honking steel beams in place on a beautiful saturday. Photos of today's activity are up on the
A few of the roof beams were placed before the wind put a stop to it. The crew turned to other pieces to be installed. Photos of today's activity are up on the
Today the hot-rolled steel section floor beams went up. The roof beams should be next. The light guage floor joists will follow but I am not sure where in the sequence. Photos of today's activity are up on the
The crew is into it now. The main frames will go in first, followed by the sub-framing. Today the first posts were lifted and temporarily bolted down until the frame is squared up and all the bolts tightened. Photos of today's activity are up on the
Steel is on site today and no time is to be wasted - they will stand it up tomorrow. Photos of today's delivery are up on the
This is where the EcoSteel Houses differ from many other prefabs. It is less of a relocation of site building techniques to a factory and more a product of a limited number manufactured components.
The frame of the living room wing is complete leaving the walls, windows, doors, and kitchen fit-out to complete. I had originally intended to document this house with a steel frame, following the construction method of the
The master bedroom wing also contains a study which can also be used as a guest room. The master bedroom has a small porch off the end which you can see here. The bedroom wing in the background has two bedrooms and a utility/laundry room.